East Devon Battery Energy Storage System (BESS) – APPEAL DISMISSED – A victory for People Power!

Devon CPRE and the Hawkchurch and Monkton Wyld Action Group are celebrating a resounding success following a Planning Inspector’s decision to dismiss a developer’s appeal to construct a large Battery Energy Storage System (BESS) at Raymond’s Hill, near Hawkchurch, in East Devon.

With the backing of Devon CPRE, the local action group had fiercely fought a proposal for a BESS the size of a factory, consisting of large metal battery containers set in rows on concrete, on open farmland at Hawkchurch. The contested site was close to both the West Dorset and Somerset county boundaries and the Axminster Substation and directly above an important aquifer, relied on by many households and farms as their sole source of drinking water. Opponents of the development were particularly concerned about the high risk of fire and the ensuing contamination of these vital water supplies. 

An appeal hearing was held in the spring after Clearstone Energy Limited appealed against East Devon District Council Planning Committee’s decision to refuse planning permission. Disappointingly, however, EDDC subsequently withdrew its opposition and stated that the appeal should be allowed, leaving the action group to fight the appeal alone, as a Rule 6 party. 

In her appeal decision, published on 13 August, Planning Inspector Helen Heward said the main reasons for dismissing the appeal were: 

i) The risk of a fire event and whether, in the event of a fire, the proposed fire safety and pollution control measures would be sufficient to prevent pollution of aquifers and control the quality of groundwater, with particular regard to the health and safety of local residents. 

ii) The effect of the proposal upon the character and appearance of the local area including the Dorset National Landscape. 

Penny Mills of Devon CPRE says, “This is a very important decision and a victory for people power. I hope East Devon District Council take note! It should give encouragement to others opposing similar BESS proposals in the countryside. We’re particularly pleased to see how thorough the inspector’s report is; it is extremely detailed and runs to over 100 points. We had submitted two objections to the proposal as well as a written representation to the appeal.

“We have been campaigning against Battery Energy Storage Systems for several years because they are so dangerous. While most people know little about them, this report and the inspector’s decision show that the powers that be are starting to take notice of the very real fire and pollution risks, and the threat of industrialising the countryside.” 

It’s the third time the Hawkchurch and Monkton Wyld Action Group has successfully fought off BESS proposals – Pound Road in 2023, Pound Farm in 2025 and now Hawkchurch. They are still awaiting the appeal decision regarding another large-scale BESS at Newlands (80MW, Ref. 24/2650/MFUL).

In the run-up to the latest appeals, we produced a video outlining the concerns of East Devon residents living in and around Hawkchurch in light of the influx of BESS proposals: The rural East Devon community urgently raising funds to fight off Battery Energy Storage Systems

related posts

Planning refusal for a small number of new homes, is a big win for Black Torrington

We’ve welcomed Torridge District Council’s decision to refuse planning permission for a clutch of new homes on a sensitive site on green fields outside the…

Read Post

We’ve objected to the 2,000 new home so called ‘Clyst Village’.

Devon CPRE objects to strategic-scale new settlement in East Devon with the misnomer ‘Clyst Village’  We’ve lodged an objection to a proposed development of up…

Read Post

Seminar – Understanding the Grid, and Battery Energy Storage Systems. 24th September 2026, 7pm, Alverdiscott Village Hall, Stoney Cross, Bideford EX39 4PZ

Seminar - Understanding the Grid, and Battery Energy Storage Systems. Thursday 24th September 2026. 7pm. Alverdiscott Village Hall. With communities across Devon facing a growing number of proposals for solar farms, Battery Energy Storage Systems (BESS), larger wind turbines, offshore wind farms and potentially a major AI data centre, questions about our electricity infrastructure are becoming increasingly important. Is there actually enough local Grid capacity?

Read Post

Come and meet us at the summer shows!

We’ve been out and about this summer at several of the one day agricultural shows throughout the County. This year, our stand is focussed on…

Read Post

Torridge Battery Energy Storage System (BESS) – Appeal lodged

In July, Torridge District Council’s Planning Committee voted to refuse proposals for a Battery Energy Storage System with a capacity of up to 99.4MW including…

Read Post

East Devon Battery Energy Storage System (BESS) – APPEAL DISMISSED – A victory for People Power!

Devon CPRE and the Hawkchurch and Monkton Wyld Action Group are celebrating a resounding success following a Planning Inspector’s decision to dismiss a developer’s appeal…

Read Post