Hartnoll Farm, Tiverton – Appeal dismissed. February 2025

We are delighted to report that this appeal has been refused by the Planning Inspectorate.  The appeal had sought to overturn the refusal decision made by Mid Devon District Council in respect of a 3.9 hectare extension to the existing business park and up to 150 homes.

The application was originally considered by the Council’s Planning Committee in January 2023, when planning permission was refused. A public inquiry was then held in September 2023 and the Planning Inspector issued their decision in October 2023, which was to uphold the Council’s original planning decision.

However, despite the decision the applicant then challenged the Inspector’s decision through the High Court and as a result, the court ordered the appeal to be re-determined with a further public inquiry, which ran from 26 November to 6 December 2024.  But in determining this appeal, the new Inspector has again found in favour of the Council and dismissed the appeal. Good news!

related posts

Could the Devon Data Monster cost North Devon’s Unesco Biosophere Reserve its designation?

Its been reported that North Devon could lose its UNESCO Biosphere designation if the Data Centre plan goes ahead. This confirms our worst fears about…

Read Post

North Tawton Solar Farm – Growing opposition to West Devon application

Devon CPRE has objected to a planning application to build a solar farm and associated infrastructure on 30 acres of good agricultural land south of Arla…

Read Post

Local Government Reorganisation – Paused.

Devon CPRE welcomes the government’s decision to review its plans for local government reorganisation and pause work on proposals affecting Devon. The government announced yesterday…

Read Post

Planning refusal for a small number of new homes, is a big win for Black Torrington

We’ve welcomed Torridge District Council’s decision to refuse planning permission for a clutch of new homes on a sensitive site on green fields outside the…

Read Post

We’ve objected to the 2,000 new home so called ‘Clyst Village’.

Devon CPRE objects to strategic-scale new settlement in East Devon with the misnomer ‘Clyst Village’  We’ve lodged an objection to a proposed development of up…

Read Post

Seminar – Understanding the Grid, and Battery Energy Storage Systems. 24th September 2026, 7pm, Alverdiscott Village Hall, Stoney Cross, Bideford EX39 4PZ

Seminar - Understanding the Grid, and Battery Energy Storage Systems. Thursday 24th September 2026. 7pm. Alverdiscott Village Hall. With communities across Devon facing a growing number of proposals for solar farms, Battery Energy Storage Systems (BESS), larger wind turbines, offshore wind farms and potentially a major AI data centre, questions about our electricity infrastructure are becoming increasingly important. Is there actually enough local Grid capacity?

Read Post