Status: Permitted

Crinnacott Farm, Pyworthy Solar Farm (50 acres) – Permitted

  1/0883/2012/FULM          Proposed PV solar farm with associated infrastructure – AFFECTING A PUBLIC RIGHT OF WAY    50 acres:      Crinacott Farm Pyworthy Holsworthy Devon EX22 6LJ…

Southcombe Farm, Shebbear Solar Farm (6 acres) – Permitted. Operational

  1/0724/2012/FULM | Installation and operation of a solar farm and associated infrastructure, including PV panels, mounting frames, inverters, transformers, fence and pole mounted security…

Derriton Fields Farm, Holsworthy Solar Farm (35 acres) – Permitted

  1/0978/2012/FULMInstallation of a solar farm and associated infrastructure – 14.8ha 11.2MW Derriton Fields Farm Holsworthy Devon  EX22 6JX 35.5 acres Permitted

Rexon Cross, Broadwoodwidger Solar Farm (25 acres) – Permitted. Operational

  1/1054/2012/FULM | Proposed Solar Park. | Rexon Cross Broadwoodwidger Devon PL16 0JJ 25 acres Permitted. Operational

Foxcombe Farm, Hollacombe, Nr Holsworthy Solar Farm (40 acres) – Permitted

  1/0817/2012/FULM | Installation of a 40 acres solar farm including up to 11 buildings to house electrical equipment | Land At Foxcombe Farm Hollacombe…

Land Near Gammaton Moor, Alverdiscott Solar Farm (24 acres) – Permitted

  1/0997/2012/FULM | Construction of photovoltaic (PV) solar array and associated works | Land Adjacent Alverdiscott Substation Near Gammaton Moor Alverdiscott EX39 4QX 24 acres…

Pitworthy Farm, Pancrasweek Solar Farm (109 acres) – Permitted

  1/0833/2012/FULM  Proposed PV solar farm with associated infrastructure 109 acres Pitworthy Farm Pancrasweek Holsworthy Devon EX22 7JT Permitted

Langlands Farm, Morchard Bishop Wind Turbine – Permitted

1 x 71m wind turbine Langlands Farm, Morchard Bishop, Crediton EX17 6RQ Allowed at appeal

West Pitt Farm, Whitnage Wind Turbines – Permitted

09/01330/FULL | Erection of 2 wind turbines, 25m high | Land at NGR 302930 116185 West Pitt Farm Whitnage Lane Whitnage Devon EX16 7DU Permitted

Thornes Farm Shop, Stockleigh Pomeroy Wind Turbine – Permitted

10/01446/FULL | Erection of a 11kw wind turbine 25m high (Revised Scheme) | Land and Buildings at NGR 287890 104887 (Thornes Farm Shop) Stockleigh Pomeroy…

Higher Locks Farm, Whitnage Wind Turbine – Permitted

10/01739/FULL | Installation of one 11kw wind turbine 25m high | Land at NGR 302300 115970 (Higher Locks) Whitnage Devon EX16 7DS Permitted

Elston Farm, Copplestone Wind Turbines – Permitted

11/00280/FULL | Erection of 2 x 11kw wind turbines 25m high on concrete bases | Land at NGR 278700 103013 (Elston Farm) Copplestone Devon EX17…

Nutson Farm, Chawleigh Wind Turbine – Permitted

11/00446/FULL | Erection of a 55kW wind turbine 34m high | Land at NGR 272179 111105 (Nutson Farm) Chawleigh Devon EX18 7ht Permitted

Beacon View, Stoodleigh Wind Turbine – Permitted

11/00785/FULL | Installation of 11KW wind turbine mounted 25m high | Land and Buildings at NGR 290749 118402 (Beacon View) Stoodleigh Devon EX16 9qg Permitted

Upcott Farm, Wembworthy Wind Turbine – Permitted

11/01544/FULL | Erection of an 11kW wind turbine 33m high| Land at NGR 265355 109332 (Upcott Farm) Wembworthy Devon EX18 7SB Permitted

Hill Farm, Uplowman Wind Turbine – Permitted

11/01876/FULL | Erection of a 50kW wind turbine 35m high and associated infrastructure | Land at NGR 301828 117186 (Hill Farm) Uplowman Devon EX16 7PE…

Edgeworthy Farm, Nomansland Wind Turbines – Permitted

11/01955/FULL | Erection of two 20kW wind turbines 27m high | Land at NGR 284714 114143 (Edgeworthy Farm) Nomansland Devon EX16 8NL Permitted

Barton Farm, Hittisleigh Wind Turbine – Permitted

12/00546/FULL | Erection of 10kw wind turbine 18m high and service box | Land at NGR 273430 095636 Barton Farm Hittisleigh Devon EX6 6LX Permitted

Park Farm, Woolfardisworthy Wind Turbines – Permitted

12/01454/FULL | Installation of 2 wind turbines mounted on an 18m lattice tower with a maximum tip height of 24.5m | Land at NGR 284344…

Hill Farm, Uplowman, Wind Turbine – Permitted

13/00182/FULL | Retention of a 50kW wind turbine 35m high and associated infrastructure | Land at NGR 301850 117212 (Hill Farm) Uplowman Devon EX16 7PE…

Appledore Farm, Bow Wind Turbine – Permitted

13/00339/FULL | Erection of a 50kW wind turbine with a maximum hub height of 24.6m and maximum tip height of 34.2 m with associated infrastructure…

Higher Henceford Farm, Black Dog Wind Turbines – Permitted

13/01617/FULL | Erection of 3 x 17m high Evance R9000 5kW wind turbines Land at Wind Turbine 1 NGR 282040 111799, Turbine 2 NGR 282030…